  • Rail Grinding/Milling

    General track care and maintenance, including milling and grinding of MetroLink rail located throughout the system, to maintain safe and effective operations.
  • Grade Crossing Repair/Maintenance

    Renewal of grade crossings where MetroLink tracks cross area roadways in Missouri and Illinois, including 4th Street, Broadway, Ewing and Plymouth. Includes work on rail, ties, concrete panels, drainage, asphalt.
  • Contact Wire Replacement

    On-going project to replace contact wires, which are part of the overhead power system that connects with the pantograph on top of MetroLink trains to supply power to the vehicle. This wire wears down from contact and regularly needs to be replaced.
  • Hybrid Bus Procurement

    Metro Transit received nearly $10.4 million from the FTA to expand its electric bus fleet with the purchase of approximately 10 new, hybrid-diesel electric buses from GILLIG. The new hybrid diesel-electric buses have dual propulsion capabilities, allowing them to operate using electricity or fuel, and they can recharge using their diesel engines.
  • MetroLink Software Enhancements

    Upgrade of the MetroLink Supervisory Control Automated and Data Acquisition (SCADA) system that monitors and controls MetroLink train movement, traction power, track signals, and switches. Replaces and upgrades monitoring and control systems at all 38 stations.
  • Communication Network Maintenance & Upgrades

    This effort is a combination of several projects including installation and replacement of microduct fiber optic cables along the MetroLink tracks, and repairing cable anchoring in MetroLink tunnels, to strengthen train/track communications and real-time security camera surveillance.
  • New Fare Collection System

    This project is transforming Metro’s fare collection system, beginning with the installation of new validators on Metro buses for testing. The entire project will upgrade validation at all vehicles and at all transit centers, MetroLink platforms, ticket vending machines, offering easier and more convenient ways to pay and manage transit fares – including new mobile […]
  • Light Rail Vehicle (LRV) Replacement

    Siemens Mobility Inc., has been awarded a contract to provide Metro Transit with up to 55 new light rail vehicles to replace aging MetroLink vehicles that have been in service for more than 20-30 years. Concept: Next-generation MetroLink vehicle provided by Siemens Mobility. Copyright Siemens 2022 Concept: Next-generation MetroLink vehicle provided by Siemens Mobility. Copyright […]
  • Downtown Tunnel Repairs and Fire Suppression Upgrades

    Crews are performing needed structural maintenance and repairs on the downtown tunnels MetroLink uses, which are more than 150 years old. This includes construction of new piping and fire suppression to ensure safety on the MetroLink system.
  • New MetroLink Customer Information System

    Upgrading and replacing outdated technology on the light rail system with new LCD video message boards, enhanced audio, real-time vehicle tracking, so customers have stronger and more thorough access to transit information. New technology has been installed at four MetroLink stations (Emerson Park, JJK Center, Washington Park, College) with work in progress at 5th & […]
  • MidAmerica Airport MetroLink Extension

    This St. Clair County Transit District project is building a 5.2 mile extension to the MetroLink light rail system, connecting the Shiloh-Scott Station to a new MetroLink Station at MidAmerica St. Louis Airport in Mascoutah – the first new station to the system since Cortex Station opened in 2018.
  • MetroLink Green Line Project

    This proposed 5.6-mile MetroLink line, with ten stations, will provide transfer capabilities to existing MetroLink Red and Blue Lines. Running from Fairground Park at Grand Boulevard along Natural Bridge Avenue, and east to Jefferson Avenue, then south to Chippewa Avenue in South St. Louis, the Green Line will feature modern in-street light-rail technology designed to […]
  • MetroLink | General Maintenance

    Crews are continuously performing necessary maintenance, repairs and upgrades throughout the MetroLink light rail system on an on-going basis. In addition to rail grinding and maintenance, other general work includes painting the Skinker Bridge, installation of new safety tactile strips at Emerson Park and 5th & Missouri Stations, replacement of jet fans in Cross County […]
  • Secure Platform Plan – Phase III

    Phase III construction adds new SPP infrastructure – security gates, fencing, surveillance cameras – to the remaining unmodified MetroLink stations, including: Lambert Airport stations, North Hanley, UMSL North, UMSL South, Rock Road, Wellston, Shrewsbury-Lansdowne I-44, Sunnen, Maplewood-Manchester, Brentwood I-64, Richmond Heights, Clayton, Forsyth, University City-Big Bend, Skinker, Stadium, 8th & Pine, Convention Center, Laclede’s Landing, […]